This is the latest in a series of regular updates planned for the
2018-19 academic year which will keep you informed on progress of the McClay
Library Phase 3 expansion project.
The project is progressing well and moving into several new areas of the
Library. Further details are provided below:
Student Lounge
Work in
this area will start on 24 June. A hoarding will be erected to shield students
from ongoing work and the size of the space will be reduced as a result. Access
to some of the vending machines and one of the water filters will be
maintained. However, there will be no toilet facilities in this area.
Special
Collections
Work on the extension to the Special Collections store
will necessitate contractor access via staircase 1 and the Special Collections
Reading Room. As a result, Special Collections readers will be relocated to the
Special Collections Seminar Room over the summer period.
Language
Teaching Room
This room will be unavailable from 24 June – over the
summer it will be used by contractors as an access route to the student lounge
area. However, the Language Resource Room at the bottom of the atrium will
remain available.
Replacement Book Return Sorter
The book return sorter is due to
be replaced this summer as the existing equipment is at end of life. The
installation project will take place between 24 June and 6 July. During this
period, only manual book returns via the Borrower Services desk on the ground
floor will be possible.
While we will do our utmost to minimise any disruption (and particularly
disruptive work will be completed out of hours or carried out as early in the
morning as possible), please note that this is a major building project so there
may be some background noise.
If you have any particular feedback or questions, please contact: library@qub.ac.uk.